Loom power cost: how much per metre, and how to cut it

The power bill arrives every month, but the real question is how much power cost went into one metre of cloth. That number goes into your costing and your job rates.

After yarn, power is often a weaving unit's biggest running cost. The bill comes for the whole unit, so many units never know how much power went into a metre. This guide covers the formula, a full worked example, getting the real load from the bill, and ways to bring the cost down.

The formula

Power is sold in units (kWh): a 1 kW load running for 1 hour is 1 unit.

Units a day = kW × hours × looms
₹ a day = units × ₹ per unit
₹ per metre = ₹ a day ÷ (one loom's metres a day × looms)
₹ a month = ₹ a day × days

Example

24 waterjet looms, 2.5 kW each, running 24 hours a day. Power at ₹8 a unit — an example rate only; use the rate on your bill. Each loom weaves 373 m a day (600 RPM, 50 picks, 85%, two 12-hour shifts).

  • Units a day: 2.5 × 24 × 24 = 1,440 units
  • ₹ a day: 1,440 × 8 = ₹11,520
  • Metres a day: 373 × 24 = 8,952 m
  • ₹ per metre: 11,520 ÷ 8,952 = ₹1.29
  • Month (30 days): 11,520 × 30 = ₹3,45,600

Put your own numbers into the Power cost per metre calculator. If you don't know the metres a day, get them first from the Loom Production calculator.

Get the real load from your bill

The kW on the motor plate is not the real load — a loom draws more at some times and less at others. The best way is a sub-meter on one loom. Without one, use the monthly bill:

Real kW per loom = units in the month ÷ looms ÷ days ÷ hours a day

Example

The bill shows 43,200 units for 24 looms, 30 days, 24 hours: 43,200 ÷ 24 ÷ 30 ÷ 24 = 2.5 kW per loom. This includes lights, fans and pumps — which is right, because that cost lands on the cloth too.

Besides the energy charge, a bill has fixed / demand charges and duty. So check once more: the bill's total ÷ the month's total metres. Say the bill is ₹3,60,000 (example) and the metres 8,952 × 30 = 2,68,560 — the real power cost is ₹1.34 a metre, above the ₹1.29 from the unit rate alone.

The compressor and pump share

On airjets, the compressor takes a large share of the power. Divide the compressor's units (from its sub-meter) among the airjet looms running and add that to each loom's kW — otherwise the airjet costing comes out far too low. On waterjets, the water pump, filters and treatment motors run too; share those over the looms as well. The right share depends on the loom model and setup — measure it on your meter, don't guess. For the difference, see the Waterjet vs Airjet guide.

Lower efficiency means more power per metre

If the same loom runs at 75% instead of 85%, its metres a day fall from 373 to 329.18 m. The power stays about the same — compressors, pumps and lights keep running. Per metre: one loom's ₹480 a day ÷ 329.18 = ₹1.46, ₹0.17 more on every metre. That's why the biggest power saving is often raising efficiency.

Ways to cut power

  1. Switch off idle looms. Waiting for a beam or a mechanic? Turn off the loom and its pump or air line.
  2. Air leaks. On airjets, leaks keep the compressor working for nothing. Listen to the air line at night when the looms are off.
  3. Only the pressure you need. Compressor pressure above what's needed costs extra power. Set it as the loom's maker advises.
  4. Power factor. Look for the power factor on your bill. If it's low there may be a penalty — have an electrician check the capacitors / panel. Your connection's rules are in the power company's tariff.
  5. Maintenance. Loose belts, dry bearings and dirty filters all add load to the motor. Oil and clean on a fixed day.
  6. Contract load. Take the load you need — too much wastes fixed charges, too little brings penalties. Read the tariff on your bill.
  7. Lights and fans. Swap old bulbs and tubes for LEDs — a small cost that saves every month.

Common mistakes

In Loomiro

In Loomiro's Costing, set the loom's kW and your ₹ per unit once as defaults. The loom's metres a day come from RPM, efficiency and shift hours, and power per metre is worked out on them — in the full breakdown with yarn, wages and overheads. The "What if…" table shows how much the cost moves when efficiency changes.

The kW, ₹8 a unit and bill amount in this guide are examples only. Use the numbers from your own bill and meter, and confirm tariff rules with your power company.